Cascade Power Project
The project won Project Finance International’s 2020 Canadian Power Deal of the Year.
The project is strategically located 12 km southwest of Edson, approximately 200 km west of Edmonton, in proximity to significant gas production sites, as well as the NGTL System and high voltage electrical transmission lines.
Once it reaches commercial operation in 2023, the facility will be the largest and most efficient combined-cycle power plant in the Alberta, utilizing two single shaft SCC6-8000H industrial turbines supplied by Siemens Energy under a long-term service agreement.
On August 28, 2020, the project’s partners successfully closed financing on the C$1.5 billion project.
Macquarie acted as exclusive financial advisor and debt arranger to the partnership, securing non-recourse project financing. The syndicate of lenders was comprised of National Bank of Canada, ATB Financial, Nomura Corporate Funding Americas, LLC, MUFG Bank, Ltd., Canada Branch, ING Capital LLC, Macquarie Capital Funding LLC, Siemens Financial Ltd., Natixis, New York Branch, Fiera Private Debt Fund VI LP and Canadian Western Bank.
The financing also involved an equity investment by OPTrust which closed on September 9, 2020. The investment was structured through an innovative and precedent setting partnership with Indigenous Communities Syndicate LP (“ICS”), a consortium of six Alberta First Nations represented by Backwoods Energy Services, one of the largest diversified Indigenous-owned businesses in Canada.
The transaction was also the first supported by the Alberta Indigenous Opportunities Corporation (“AIOC”), who provided a C$93 million loan guarantee supporting the credit and financing arrangements.
Further information on the financing can be found on Business Wire’s website and on backwoodsenergy.ca.
It is anticipated that the project will supply more than 8% of Alberta’s average power demands and represents a significant opportunity in the province’s transition off coal-fired power to a lower carbon intensive power grid. Output from the project has already been contracted and the facility has also secured long-term gas netback agreements, providing cashflow stability for the investors.
The Cascade Power Project is being developed and will be operated by Kineticor Resource Corp. (“Kineticor”) on behalf of a partnership that includes
- OPTrust invests and manages one of Canada’s largest pension funds with net assets of over C$25 billion and administers the OPSEU Pension Plan (including OPTrust Select), a defined benefit plan with over 100,000 members
- Indigenous Communities Syndicate, a consortium of six First Nations, owned by Alexis Nakota Sioux Nation, Enoch Cree Nation, Kehewin Cree Nation, O’Chiese First Nation, Paul First Nation and Whitefish Lake First Nation
- Axium Infrastructure Inc., an independent portfolio management firm experience acquiring, developing, financing, operating and managing infrastructure assets
- DIF Capital Partners, a leading global independent infrastructure fund manager, with €7.6 billion of assets under management across nine closed-end infrastructure funds and several co-investment vehicles
Further information on the project can be found at cascadepower.ca.
Torys also acted on the following in connection with this project:

| Jurisdiction | Yellowhead County |
| Province/State | Alberta |
| Country | Canada |
| Nature of Engagement | Project Finance, Environmental, Project Development, Energy Regulatory |
| Client | Cascade Power Project LP |
| Client Role | Project Owner |
| Value | $1,500,000,000 CAD |
| Key Features | Indigenous involvement |