Authors
On September 21, the Government of Canada introduced Bill C-39, the Building Canada Strong Act (Bill C-39)1, in the House of Commons, which aims to bring greater speed, certainty, and predictability to federal project reviews. It does so in part by incorporating several of the efficiencies first introduced in 2025 for projects of national interest under the Building Canada Act regime. Those include a consolidation of federal decision-making, operationalizing the promised two-year approvals process timeline, and centralizing the administration of federal approvals—as well as Indigenous consultation—into one responsible authority per project. Bill C-39 also introduces a mechanism for designating “Regions of National Interest”, in which certain project-types within a defined region will be eligible for the accelerated pathway applicable to scheduled projects of national interest.
At the same time, the Government of Canada issued a complementary Cabinet Directive on Getting Projects Built in Canada (the Cabinet Directive)2, providing direction to the public service on the new timeline for federal project decisions and clarifying roles and responsibilities across relevant federal entities. Taken together, Bill C-39 and the Cabinet Directive take meaningful steps to accelerate and centralize project approvals without materially overhauling the nuts and bolts of the established and complex regulatory processes in place.
Bill C-39 has been highly anticipated since the federal government published a discussion paper in early May3, undertook public engagement that was extended until late July, and finalized amendments to the Physical Activities Regulations before the House of Commons returned. The bill is expected to move swiftly through the legislative process and, subject to changes made in Parliament, is poised to become law in the near term.
As federal project assessment and permitting regimes have become more complex in recent decades, the Government of Canada has faced mounting criticism of inefficiencies, duplication, and lack of coordination across the now 14 federal entities that play a role in regulating energy, mining, and infrastructure projects4.
Following the lead of the Building Canada Act, Bill C-39 proposes to consolidate federal decision-making by reducing the number of departments and agencies involved in project decisions, and by establishing mechanisms for decisions from multiple departments and agencies to be included in a single decision document.
Although conditions rooted in several statues will in many cases be consolidated into a single document, enforcement would continue to be carried out by each federal department responsible under existing legislation. For example, if a mining project obtained a single decision document containing approval conditions rooted in the Impact Assessment Act as well as conditions developed to meet the requirements of the Explosives Act, an enforcement action related to the former would be carried out by IAAC while an action related to the latter would be managed by Natural Resources Canada.
Alongside these reforms, the Government of Canada has been working to further consolidate federal decisions by reducing the instances when a project is designated for a federal assessment in the first place12, or seeking to rely on provincial environmental assessment processes to undertake all or part of the assessment. The Canada-British Columbia Agreement has been in place since 2019, allowing British Columbia-led assessments to substitute federal assessments. Now, Canada has final cooperation agreements with the remaining provinces—except Québec, which is still in draft, and Saskatchewan, which is being negotiated. Each vary in their scope, but broadly allow for all or part of an environmental assessment to be led provincially for certain categories of projects.
The Government of Canada set a clear policy objective that federal regulatory decisions for projects should be issued no more than one year after the proponent provides a comprehensive application and the required information and studies, which itself has now been reduced to a one-year period. In parallel with Bill C-39, the government published the Cabinet Directive replacing a similar directive from 2024 and making the more ambitious timeline of a one-year evaluation and decision-making process for federal approvals explicit across the over 14 federal entities that are involved in project regulation13. Bill C-39 operationalizes this objective by adjusting the presumptive legislated timelines for projects regulated by IAAC, CER, and CNSC.
For the IAAC process, the one-year government review and decision-making period would begin at the “notice of commencement” stage, which falls one year after the proponent has submitted its required information and studies, for a total of two years of process time. Bill C-39 would reduce IAAC’s evaluation timelines from 600 to 300 days for the report stage and from 120 to 65 days for the Minister and/or Cabinet to deliberate on and render its decision, for a total of 365 days. The bill does, however, contain several extension provisions:
A new section is also proposed stating that if the Minister does not issue a decision statement within 365 days of the notice of commencement, they must post a notice with the reasons why the timeline was missed15. This is a transparency and accountability mechanism that does not trigger any automatic approval or refusal, does not create any specific right of action, and adds no additional legislative timeline for when the Minister must issue the decision statement after the notice is posted.
Bill C-39 adjusts the legislated timelines for projects regulated by the CER and CNSC so that federal decisions are made within one year of the posting of their respective completeness of information determination.
Federal permits are expected to be completed concurrently with the IAAC, CER, or CNSC processes within the one-year timeline. Although proponents have been seeking concurrent reviews for some time, these shorter legislated timelines, combined with the Cabinet Directive, are designed to ensure the public service coordinates to achieve that objective. These changes represent a marked acceleration of the five-year target for federal impact assessments and permits for a project (two years for projects that do not require an impact assessment) that the previous government committed to in 202420.
One of the most interesting and flexibility-providing features of Bill C-39 is the new broad ministerial power to grant an order allowing construction and related early works before the IAAC or CNSC process has concluded. The Minister of Environment or CNSC may do so where it is considered “in the public interest” and the early works activities would be subject to conditions21. For the IAAC process, the Minister is also authorized to grant additional federal authorizations (including, for example, Species at Risk Act or Fisheries Act permits) required for the relevant early work, provided that the requirements of the federal statues governing those authorizations still apply22.
Overall, that means projects now have a path to carry out whatever early works the Minister determines are in the public interest, providing proponents a mechanism to raise and pursue meritorious early work. Because the mechanism is an order power, it also means that there will be a formal process to follow where public comment will be sought, Indigenous groups will be consulted, and each order can be challenged through the courts.
While this new power does not apply to the CER process, the Canadian Energy Regulator Act already includes powers to exempt narrow categories of projects from requirements before a certificate is issued or dismissed23.
The Government of Canada has been working to adopt reforms intended to avoid delay while fulfilling its constitutionally mandated duty to consult and, where appropriate, accommodate Indigenous Peoples whose rights may be impacted by a proposed project. The duty to consult process requires meaningful, two-way dialogue with Indigenous Peoples whose rights are potentially impacted by such a proposed project, aiming to address their concerns and, where appropriate, provide accommodation. Project proponents are expected to engage and consult meaningfully with Indigenous groups early in the project development process to obtain and maintain regulatory approvals, with the aim of minimizing risks of delay and dispute.
The Cabinet Directive aims to improve efficiency and reduce consultation burden on Indigenous groups by establishing a new Crown Consultation Hub at IAAC to coordinate direct Indigenous consultation for project reviews by the Crown, except for where the CER and CNSC are the sole assessor, or the project is being coordinated by the Transportation Project Office, Northern Projects Management Office, or the Major Projects Office. This clarification of which federal entity is the Crown’s lead on Indigenous consultation for a given project is intended to guide the public service, Indigenous communities, project proponents, and others involved in the regulatory process.
Bill C-39 does not change Canada’s duty to consult Indigenous Peoples or its obligations under modern treaties for impact assessments or federal permitting. The proposed amendments to the Canadian Energy Regulator Act process, and forthcoming regulations under the Impact Assessment Act, will expressly allow extended timelines to complete Indigenous consultations where required in the circumstances. The CNSC process contains broader timeline extension powers that can be exercised in the context of Indigenous consultations.
Just over a year ago, the Government of Canada passed the Building Canada Act to establish a streamlined process for approving projects that are designed as a “Project of National Interest”. Bill C-39 now proposes to expand the scope of the Building Canada Act to enable the designation of a “Region of National Interest”, which could include areas such as transportation or energy corridors, telecommunications networks, energy production and transmission systems, and industrial regions, and could be established for current or future development needs24.
Under the proposed new process, a regional assessment under the Impact Assessment Act (or the applicable federal legislation for the territories) would be a precondition to any designation of a Region of National Interest. Because that preliminary step can be a multi-year exercise, it will limit the acceleration potential of the new process, at least over the near to medium term.
A Region of National Interest designation will include geographic coordinates along with a list and description of development types, as well as eligibility criteria for the projects that will be eligible for the accelerated approvals pathway currently only available under the Building Canada Act for Projects of National Interest25.
This new Regions of National Interest framework mirrors the existing framework for Projects of National Interest under the Building Canada Act, except for that Regions of National Interest must be made by Cabinet as opposed to the Minister. As a result, a judicial review or other court challenge would be made on the Governor in Council decision rather than ministerial decision. Of all the proposals in Bill C-39, this “Regions of National Interest” concept is the most novel addition to Canada’s project approvals process.
Finally, Bill C-39 includes a suite of legislative changes to modernize outdated requirements, reduce duplication, streamline permitting requirements, and move projects from application to construction faster. These include:
Not all the proposals in the federal government’s discussion paper30 made it into the Bill. Most notably, the discussion paper proposed to give Cabinet a limited power to exempt specific projects from the application of the jeopardy test under the Species at Risk Act if it’s in the public interest and the proponent has made all reasonable efforts to avoid or reduce the impacts on at-risk species. Following significant opposition during the spring and summer engagement period from the environmental community, this proposal was not included in Bill C-39.
Bill C-39 includes further proposed changes to the Canada Transportation Act related to port governance and security, and to the Canada Labour Code related to collective bargaining and workplace protections that are not covered by this bulletin.
As outlined in the Cabinet Directive, the Major Projects Office will continue to play a role providing strategic direction, coordinating across federal departments and agencies, supporting Crown-Indigenous engagement and consultations, and leveraging its financial expertise to support final investment decisions. The President of IAAC is also given an explicit role as the “Federal Review Coordinator” responsible for developing necessary policy tools, maintaining a public dashboard, and providing a point of contact for proponents and other jurisdictions. In addition to implementing Bill C-39 once adopted, all relevant departments and agencies are expected to demonstrate their progress and report on results.
To discuss these issues, please contact the author(s).
This publication is a general discussion of certain legal and related developments and should not be relied upon as legal advice. If you require legal advice, we would be pleased to discuss the issues in this publication with you, in the context of your particular circumstances.
For permission to republish this or any other publication, contact Bryn Turnbull.
© 2026 by Torys LLP. All rights reserved.